Confusion between SIRIM testing and ST COA is a leading cause of delays.
SIRIM testing (safety + optional EMC) → qualified report → ST COA application and approval. Both are mandatory.
II. Full 2026 Process
1.Preparation & Product Assessment: 1–2 weeksConfirm ST controlled list, secure local Malaysian holder, prepare bilingual documents (English/Malay) with consistent model info.
2.Sample Testing: 4–6 weeks
·Mandatory electrical safety for all controlled products.
·EMC mandatory for IT/AV, wireless accessories, high-power appliances.
·CB reports shorten to 3–4 weeks.
·Failure adds 2–4 weeks per retest.
3.Document Submission & Official Review: 2–4 weeksSIRIM QAS review → ST review. Inconsistent documents cause 1–2 weeks delay per correction.
4.Factory Audit (PCS only): 2–4 weeksOn-site inspection mandatory in 2026 (no remote audits). ISO 9001 simplifies process.
5.COA Issuance, Label Purchase & Affixation: 1–2 weeksLabels applied to product body per official format.
III. Total Timeline
·Mode A (BTS, no audit): 1.5–3 months (1.5–2 months with CB)
·Mode B (PCS, with audit): 4–8 monthsDelays from testing failure or audit non-conformity.