CB certification is widely used for export but often misunderstood. This guide covers documents, timeline, validity, and changes based on 2026 on-the-ground experience.
1. Company Basic Documents
·Business license (with stamp, sometimes English translation)
·CB application form
·Power of attorney (for agencies)
·Factory info form (only CB-FCS)
2. Core Product Technical Documents
·English user manual
·Schematics, PCB layout
·BOM / CDF with critical components
·Product specification
·Label/nameplate design
·Internal/external product photos
3. Product-Specific Documents
·Batteries: Cell specs, BMS design
·Lighting: LED driver data (ACP for photobiological)
·Lasers: Laser level documentation
·Smart products: Software safety logic
4. Non-Required Documents
RoHS, energy efficiency, network access licenses are not mandatory for CB.
II. 2026 CB Certification Timeline
-Document preparation: 1–2 weeks
-Sample delivery: 2–5 days
-Testing:
·Simple: 2–3 weeks
·Medium: 3–5 weeks
·Complex/batteries: 5–8+ weeks
·ACP products: 3–5 weeks
-Report & NCB review: 1–2 weeks
-Certificate issuance: 1–3 days
Total lead time:
·Simple: 3–4 weeks
·Medium: 4–6 weeks
·Complex: 5–8+ weeks
Start at least 2 months before shipment.
III. Validity & Modification Rules
·No fixed IECEE validity; depends on standard and product changes.
·Type A (non-safety): unlimited changes
·Type M (safety): most NCBs limit to 3 changes
·IEC 62368-1:2018 invalid after 7 Dec 2025
IV. 2026 Core Rules
·ACP mandatory for IEC 62471 / IEC 60825-1
·IEC 62368-1:2023 mandatory for new applications
·Stricter review of document authenticity and product consistency