MIC Certification Process & Timeline (2026 Practical Version)

2026-03-06

The biggest delays come from wrong agent, missing documents, and failed testing. Cybersecurity is now fully integrated.

I. 2026 Core Process

1.Determine Risk Tier (1–3 days)General / High‑Risk / Critical InfrastructureWrong tier = full rework.

2.Prepare Documents & Samples (3–7 days)

·Specs, schematics, BOM, Korean manual

·New: Cybersecurity Report + Vulnerability Plan

·2–3 identical mass‑production samples

3.Lab Testing

·General: 7–15 days

·Smart devices: 15–20 days

·High‑risk: 2–4 weeks

4.Agent Submission & Review

·General: 3–5 days (online)

·High‑risk: 1–2 weeks (Korean hard copies)

5.Receive Number & Labeling (1–3 days)Mark MIC number permanently on the product.

  II. Total Lead Times (2026)

·Basic low‑power: 15–25 days

·Standard smart devices: 25–40 days

·5G / V2X / high‑end: 40–60 days

·Critical infrastructure: 60–90 days